November 2009
The winter months always slow down our
project somewhat, short daylight hours and cold temperatures are not
conducive to rapid progress! Recently it has been rare for us both to be
up at the shed at the same time, for various reasons, but independently
we have both been plodding on with various tasks.
The rear axle and diff, once away from underneath the bus, has been
thoroughly rubbed down, degreased, primed and top coated and is now
ready to be reinstalled. The newly exposed rear chassis framework has
also undergone the same treatment. Steve has continued to be busy
refurbishing the brake and hub components.
Following it's recovery from NNC in Taunton the formica panelling has
been fettled up for the variety of locations it was needed. First up,
the best lengths were reserved for the offside interior walls. It
appears that a change in construction occurred between CDK and NNC
rolling off the Plaxton production line - CDKs original interior
panelling was made up of coated hardboard (in the birds-eye maple
pattern) whereas NNC was sheet formica. Therefore, the recovered formica
required backing with hardboard before it could be fitted into place, so
a quick trip to the local B&Q was undertaken where some 8 x 4 sheets
were cut to shape with one of their wall mounted saw thingies - handy
that, as an 8 x 4 sheet won't fit in a people carrier! Once bonded
together and trimmed to size the 'new' interior walls were installed and
the Bakerlite capping rails screwed down. After 4 years of seeing black
stress panels it is most pleasing to see the interior walls now complete
in correct pattern original materials -something we both feared would
never happen.
|

Richard trimming formica
panels |
One item which has been regularly shunted around the workshop over the
years has been the offside emergency exit door - other than the removal
of the glass and window rubber, this item has not been touched in terms
of it's renovation. While I was attending to the interior, Steve bit the
bullet and made a start on dismantling it, first removing the lock
mechanism and then what was left of the interior panelling. Finally the
exterior aluminium skin was detached to reveal the framework which is
going to need some attention from the welder! Using the old panels as
patterns, the remainder of the recovered formica has been used to make
up new items to replace the badly damaged originals. Although having to
piece these together (as we didn't have a large enough sheet to do the
job in one go) the finished panels will do the job nicely and are a
massive improvement over the battered original. Over the winter Steve
will repair the damaged areas of the framework and then show how
skilfully he is by cutting and folding the complicated shape to form the
new exterior skin - I'll make sure I'm out of the way when he does that
one! ;-)
|

front entrance door |

showing the water damage |
A similar exercise has been carried out on the front entrance door. One
of the first tasks Steve undertook was to repair and re-skin this door
(December 2004) and we have now got around to replacing the interior
panels. The original hardboard lower panel was very water damaged at the
bottom and at some point had been 'dug' quite badly in the middle.
Luckily, following a chance conversation with another bus owner on site
a year or two ago, we were offered a 6 x 3 sheet of the elusive birds-eye
maple formica. It was a half shade darker than that in CDK but was close
enough, so we gratefully snapped it up ! It only turns out that some of
Blackburn Transport's fleet had this very pattern interior in the 60's -
how ironic! A big thank you to Steve H for the donation. This sheet has
allowed us to replace the whole of the interior skin for the door
creating a uniform colour and should look perfect once re-installed.
Into December and with increasingly short days due to temperature and
light, I've returned my attention to putting the interior back together.
During the rewiring process the sky-light areas had to be disassembled
to trace wires - this involved removing all the aluminium edging strips
and shaped channel sections which cover the wiring runs. Most of these
showed signs of years of wear and tear and have taken quite a while to
restore to their original shinny condition. The plastic surrounds to the
apertures are extremely dirty and have proved to be quite difficult to
get clean due to the textured surface. Working on these has been quite a
challenge for a 6 foot 5 chap resulting in aching shoulders and neck at
the end of the day!
We have also had a good sort out recently and collected together all the
bits and bobs which need to be or will be refitted to CDK when it is
finally repainted such as indicator units, trim, locks etc. Many of
these items have been sat in boxes in various locations over the last
few years so it has been a good exercise to gather them all into one
place.
As 2009 comes to a close it has been interesting to look back on what
has been our most productive year so far - we really have achieved quite
a lot over the last 12 months considering we only get chance to indulge
over 1 or 2 days at the weekend.
Thanks to all those who have taken the time to pass comment and give
words of encouragement - hopefully 2010 will see us much closer to the
day when we can proudly take CDK out on the road.
